Two Jobsites Need One Coordinated Building Schedule
Your buyer drives past the property and sees a foundation. No walls. No roof. Naturally, the next question is whether anything is happening. With modular construction, the answer may be hundreds of miles away. The home can be moving through factory production while crews prepare the property to receive it. That changes how buyers need to understand progress, and how the project team needs to manage the schedule. I think this is one of the most useful ideas a Realtor can explain to a client considering modular: there are two jobsites working toward the same home. The opportunity comes from overlapping compatible work. The responsibility is making sure those workstreams meet when they should. Know what can move forward at the factory Once the required design, engineering, selections, and approvals are in place, the home can move into its production process. How much work is completed there depends on the design, factory, and project scope. Structural assemblies and substantial portions o...